Housing reform, heritage and negotiated outcomes: three recent NSW planning decisions

Housing reform, heritage and negotiated outcomes: three recent NSW planning decisions

Three Land and Environment Court decisions delivered on 20 October 2026 illustrate different pathways to development approval: a negotiated modification of a renewable energy project, a housing appeal in which council's contentions were resolved but residents' concerns still required assessment, and a contested apartment proposal adjoining a heritage conservation area.¹ ² ³

 

For developers and landowners, the decisions highlight the importance of site-specific evidence, carefully targeted amendments and a clear distinction between obtaining agreement and satisfying the legal requirements for approval.

 

Key takeaways

  • Agreement with council does not end the Court's job: a modification must still be legally available, and objectors' concerns may still need merits assessment.¹ ²
  • Landscaping above a basement counted towards the Housing SEPP landscaped area standard in Antipodean; rooftop communal space did not.³
  • Housing incentives do not displace heritage or design assessment. Applicants still need a coherent design response.³

 

Bilbul: expanding battery storage through a negotiated modification

In Bilbul Renewable Energy Pty Ltd v Griffith City Council [2026] NSWLEC 1703, Commissioner Targett upheld an appeal concerning modifications to an approved solar farm and battery storage development at 394 Macedone Road, Bilbul.¹

 

The modification application initially sought to increase the number of battery energy storage units from four to eight and change the timing of landscaping required by the existing consent. Following conciliation, the landscaping timing change was withdrawn, the layout was revised and additional planning and acoustic information was provided. The parties then reached agreement.¹

 

The "substantially the same development" requirement

Agreement did not remove the need to establish that the modification could lawfully be approved. Commissioner Targett considered whether the modified proposal remained substantially the same development for the purposes of section 4.55(2)(a) of the Environmental Planning and Assessment Act 1979.¹ ⁴

 

The Court considered both qualitative and quantitative changes. The essential electricity-generating use remained unchanged, as did the approved 4.95 MVA grid connection. Although battery storage units increased from four to eight, the proposal also reduced the number of solar modules, widened landscape buffers and relocated security fencing behind the landscaping. The Court accepted that the modified development remained substantially the same.¹

 

Importantly, this was a conciliation outcome, not a contested merits determination. Commissioner Targett expressly stated that she had not undertaken a merits assessment of the issues originally in dispute.¹

 

Practical takeaway: A modification should be supported by a comparison of the approved and proposed development as a whole, not simply an account of the component being increased. In Bilbul, revised layout, landscaping and supporting evidence formed part of the agreed pathway to approval.

 

Jenner: agreement with council does not end the assessment

In Jenner v Northern Beaches Council [2026] NSWLEC 1702, Commissioner Targett granted consent to an amended proposal for two residential flat buildings at 138 Griffiths Street and 35 Lodge Street, Balgowlah.²

 

Before the hearing, the applicant and council had agreed on measures to resolve council's contentions. Nevertheless, council sought a hearing so that objectors' submissions could be considered. The Court therefore undertook its own merits assessment rather than simply giving effect to an agreement reached in conciliation.²

 

Residents' concerns produced substantive scrutiny

The Court considered concerns about height, floor space ratio, setbacks, privacy, overshadowing, tree removal, traffic and construction impacts.²

 

Some criticisms resulted in corrections or further evidence. The Court accepted that objectors' concerns about the floor space ratio calculation were well founded, and the architectural plans were amended. It also required further reasoning to justify the removal of high-retention-value trees rather than relying on the initial material alone.²

 

A height variation was accepted on the evidence, including the limited lateral extent and central location of the exceedance and the absence of additional overshadowing from the height-breaching elements.²

 

Expert independence matters

The judgment also contains a significant warning about expert evidence. The applicant's town planner had a financial interest in the development which had not been disclosed in the initial joint report. Commissioner Targett stated that she would have given that evidence very little weight had the proceedings involved a competing town planning opinion. In this case, council's expert agreed with the applicant's expert on all matters.²

 

The appeal was ultimately upheld after the Court was satisfied that the amended application and conditions adequately addressed council's original contentions and the objectors' submissions.²

 

Practical takeaway: Resolving council's contentions is valuable, but applicants must still be prepared to substantiate their proposal, correct errors and address residents' concerns. Expert interests should be disclosed clearly from the outset.

 

Antipodean: landscaped area, heritage and the emerging housing context

In Antipodean Building Group Pty Ltd v Randwick City Council [2026] NSWLEC 1701, Commissioner O'Neill approved a seven-storey residential flat building at 25–27 Church Street, Randwick. The proposal comprised 21 three-bedroom apartments, including three affordable rental housing apartments, with two basement levels.³

 

The application relied on both the low- and mid-rise housing provisions and the affordable housing provisions of the State Environmental Planning Policy (Housing) 2021.³ ⁵ Unlike Bilbul, the appeal proceeded to a contested hearing after conciliation failed.

 

Landscaping above a basement can count

A central dispute concerned whether landscaped areas above a subterranean basement could count towards the Housing SEPP's minimum landscaped area requirement.³ ⁵

 

Council's calculation excluded those areas. Commissioner O'Neill preferred the applicant's interpretation: the definition was directed to the ground-level site plan and excluded the building footprint, driveways and parking areas, but did not exclude landscaping merely because a basement lay beneath it. The Court distinguished landscaped area from deep soil, noting that the latter definition expressly addresses structures below ground.³

 

The Court therefore found that the proposal complied with the minimum landscaped area standard. However, it rejected the alternative argument that rooftop communal open space could count, because that space lay within the area occupied by the building.³

 

The distinction matters: landscaping above a basement and rooftop communal space were not treated as interchangeable.

 

Heritage assessment requires more than identifying visibility

The site adjoined the St Jude's Heritage Conservation Area. Council argued that the proposal's scale would adversely affect its heritage significance.³

 

The Court accepted that visibility as a backdrop to the conservation area was not inherently unacceptable. It examined how the building responded to the scale difference, including upper-level setbacks, its distinct building components and changes in materials and colour that made the upper levels more recessive. On that evidence, the Court found the heritage response acceptable.³

 

This was not a finding that housing reform displaced heritage assessment. The approval depended on the Court's evaluation of the proposal's particular design and its relationship with the conservation area.

 

Setbacks and future character remain design questions

Commissioner O'Neill accepted the proposed setbacks in light of window orientation, balcony screening, façade articulation and consolidated landscaping. The Court also accepted evidence that accommodating affordable housing floor space through reduced setbacks was preferable, in this proposal, to increasing the building's height and its impact on the heritage setting.³

 

The desired future character assessment looked beyond existing development alone. The Court identified the Housing SEPP's housing provisions as a primary influence on the precinct's emerging character, alongside the local environmental plan and existing development.³

 

Design excellence remained a separate requirement. The Court found it satisfied after considering the architectural treatment, public domain contribution, neighbouring relationships and sustainable design outcomes.³

 

Practical takeaway: Housing incentives do not eliminate the need for a coherent design response. Applicants should demonstrate how additional density is accommodated while maintaining acceptable landscaping, privacy, heritage and public domain outcomes.

 

What these decisions mean for applicants

Read together, the decisions support three practical priorities:

  • Choose the right approval pathway. A negotiated modification and a merits hearing involve different tasks. Bilbul required the Court to establish that the agreed outcome was legally available; Jenner still required merits assessment despite agreement on council's contentions.¹ ²
  • Resolve problems through evidence and targeted amendments. Revised layouts, corrected calculations and additional technical justification materially assisted the approval pathways in Bilbul and Jenner.¹ ²
  • Design for both transition and context. Antipodean demonstrates the importance of explaining how housing reform's increased scale can coexist with neighbouring amenity and heritage significance, rather than relying on numerical entitlements alone.³

 

For landowners considering redevelopment or modifications to an existing approval, the strongest application is one that identifies the statutory pathway early and supports the proposed outcome with coordinated planning, design and technical evidence.

 

Frequently asked questions

What happens if council and the applicant agree at a conciliation conference? Agreement is not the end of it. In Bilbul, that meant confirming the modification was substantially the same development; in Jenner, council sought a hearing so objectors' concerns were assessed.¹ ²

 

What does "substantially the same development" mean? It is the test under section 4.55(2)(a) for modifying a consent. The Court compares the approved and modified development both qualitatively and quantitatively, as a whole.¹ ⁴

 

Can landscaping above a basement count as landscaped area under the Housing SEPP? In Antipodean, yes: the Court found the definition did not exclude landscaping merely because a basement sat beneath it. Rooftop communal open space did not count.³

 

Can a development next to a heritage conservation area be approved? Yes, if the design responds to it. In Antipodean, upper-level setbacks, distinct building components and recessive materials made the heritage impact acceptable.³

 

What can I do if my development application is refused? You may be able to appeal to the Land and Environment Court. A development appeal is generally to be made within 6 months after you receive notice of the determination.⁶ Early advice helps you choose the right pathway.

 

If you are planning a development, modifying an approval or facing a council refusal, our LEC and local council team can help you map the right pathway. Book a free call

 

This article provides general information and is not legal advice.

 

Sources

[1] Bilbul Renewable Energy Pty Ltd v Griffith City Council [2026] NSWLEC 1703, 20 October 2026.

[2] Jenner v Northern Beaches Council [2026] NSWLEC 1702, 20 October 2026.

[3] Antipodean Building Group Pty Ltd v Randwick City Council [2026] NSWLEC 1701, 20 October 2026.

[4] Environmental Planning and Assessment Act 1979 (NSW) s 4.55. NSW Legislation

[5] State Environmental Planning Policy (Housing) 2021 (NSW). NSW Legislation

[6] Land and Environment Court of NSW, Development appeals.